Powered Land · AI Hyperscale · ERCOT / East Texas
A pre-positioned, powered-land platform for AI hyperscale.
A rare, permitted grid position with power infrastructure already studied and in place — delivering first power in months, not years, and a ~30-month head start over greenfield development.
The Opportunity
Power is the bottleneck for AI data centers. As ERCOT large-load queues stretch to 24–48 months, a permitted, powered-land position becomes one of the scarcest commodities in the market. This twin-site platform assembles grid, on-site gas, solar, and storage into a single, deployable, multi-source power supply — on fast timelines and with significantly reduced execution risk.
Multi-Source Power Stack
Grid Interconnection
- 150 MW permitted 138 kV interconnection in place
- +75 MW uplift under study → path to 225 MW
- Fast-track load pathways up to ~125 MW that avoid the large-load queue (3–9 months)
Energy Storage
- 300 MW / 600 MWh BESS across both sites
- Interconnection agreements executed and queue-cleared
- Firms renewable supply and enables tolling / redundancy
On-Site Gas Generation
- ~100 MW behind-the-meter (50 MW per site)
- Firm and dispatchable — not weather-dependent
- Intrastate supply — no FERC jurisdiction, faster permitting
Renewables
- 116 MW (+50 MW) utility-scale solar available
- Firmed by 600 MWh of storage for continuous compute
- Supports a credible low-carbon power product for tenants
Site & Infrastructure Readiness
Land
- ~174 acres across four parcels
- Core parcels zoned & permitted; expansion parcels entitling
- ALTA/NSPS title and topographic surveys completed
Fiber
- Three diverse routes per site via tier-1 carrier backbones
- Capacity from ≤400 Gb/s up to multi-Tb/s at metro hub
Water & Cooling
- ~34.7 Mgal/yr demand with primary + backup supply headroom
- Dry-cooler + direct-to-chip — no cooling towers
Gas Supply
- Nearby intrastate lateral supporting ~120–350 MW
- Interstate line within reach for scale; ~6–8 month lateral build
Development Status
Why It Wins
Existing interconnection work compresses first power to 6–18 months vs. 24–48 for greenfield — earlier revenue, lower capital drag.
A permitted 138 kV / 150 MW position is rare and hard to replicate as queues lengthen.
Twin-site redundancy with optionality toward a GW-class hybrid energy + compute campus.







